Solar Sanity Checksolar, decoded Independent. Nothing you type leaves your browser.

Anoka Municipal Utility

Minnesota Utility Interconnection & net metering rules
Net Metering Allowed1
NEM TypeAnnual
Line Taps Allowed0
Load Taps Allowed0
AC Disconnect RequiredYes

Net metering & export

Net Metering Allowed
1
NEM Type
Annual
TOU Utility
0
Post Solar Billing Method
Net Metering
Net Excess Generation Notes

A qualifying facility having less than 40-kilowatt capacity, the customer shall be​ billed for the net energy supplied by the utility according to the applicable rate schedule for sales to that​ class of customer. A customer with a qualifying facility or net metered facility having a capacity below 40 kilowatts​ that is interconnected to a cooperative electric association or a municipal utility may elect to be compensated​ for the customer's net input into the utility system in the form of a kilowatt-hour credit on the customer's​ energy bill carried forward and applied to subsequent energy bills. Any kilowatt-hour credits carried forward​ by the customer cancel at the end of the calendar year with no additional compensation.

Rebates Offered
0
Deregulated
1

Interconnection & taps

Approval Req To Install
Yes
Interconnection Level
3
Line Taps Allowed
0
Load Taps Allowed
0
Automatic Transformer Upgrade Size
0
Meter Aggregation Allowed
0

System size & offset

System Size Restrictions
40
System Size Restriction Type
AC kW
System Size Battery Included
0
System Size Includes Existing Systems
0
Offset Value
0
Offset Calculation Period
0
Industry Standard Watts Sqft
2
System Offset Notes

40 kW AC max

Systems over 40 kW will have a 120% offset requirement


 For interconnection of a proposed DER to a radial distribution circuit, the aggregated generation, including the proposed DER, on the circuit shall not exceed 15% of the line section annual peak load as most recently measured or 100% of the substation aggregated minimum load. A line section is that portion of an Area EPS Operator’s electric system connected to a customer bounded by automatic sectionalizing devices or the end of the distribution line. The Area EPS Operator may consider 100% of applicable loading (i.e. daytime minimum load for solar), if available, instead of 15% of line section peak load. 

Offset Calc Tool
Historical Usage

Metering & disconnect

Production Meter Required
Situational
Production Meter Criteria
  • Production meters are required for 20kW or more, or at utility's discretion
  • Customer may request a production meter even if the utility does not require one
Production Meter Position
Inv-Disco-PM-POI
Production Meter Labeling
Production Meter
AC Disconnect Required
Yes
AC Disconnect Labeling
Utility Disconnect Switch
Meter Spot Process

Disconnect of Power Scheduling Form must be submitted to the utility prior to a temporary disconnect: Form Center • Disconnection of Power Scheduling Form (New In (anokamunicipalutility.com)


  • Meter seals are NOT to be cut by contractors or by homeowner(s) and MUST be scheduled through the AMU office.

Plans & docs

Site Plan Reqs


SLD Reqs
  • Applicant name.
  • Application ID.
  • Installer name and contact information.
  • Address where DER system will be installed - must match application address. o Be sure to list the address for the protective interface equipment if the protective interface equipment is located at a different address than the DER system.
  • Correct positions of all equipment, including but not limited to panels, inverter, and DC/AC disconnect. Include distances between equipment, and any labeling found on equipment. 

One-line diagram must be signed and stamped by a Professional Engineer licensed in Minnesota if the DER is uncertified greater than 20 kW AC or if certified system is over 250 kW

Electric Service Reqs

IEEE 1547

IEEE C37

IEEE C57

IEEE C62

IEEE 519

UL 1741

NFPA 70 (2017)

ANSI C84.1

NEMA MG 1

Electrical Stamp Required
0
Equipment Approvals
California Energy Commission
Meter Num Req SLD 3LD
0
ESID Num Req SLD 3LD
0
Rate Schedule Link
link
Website
link
Phone
(763) 576-2750

Other details

Restrict Inspection
0
Revision Required
1
Mod Swap Requires Planset
1
Address ID
8691982
Express Planset Eligible
No
Compiled from public records, 2026. Tariffs and interconnection rules change; verify with Anoka Municipal Utility before you rely on this. The useful move: if an installer says you need a main panel upgrade, ask how these tap and interconnection policies were considered first.