Net Metering AllowedYes
NEM TypeMonthly
Line Taps AllowedNo
Load Taps AllowedNo
AC Disconnect RequiredYes

Net metering & export

Net Metering Allowed
Yes
NEM Type
Monthly
TOU Utility
No
Post Solar Billing Method
Net Metering
Net Excess Generation Notes

To the extent the net consumption is negative (i.e. Customer-Generator produced more kWh during the month than the Company supplied), the Customer-Generator will be credited in accordance with the Company’s bi-annually calculated avoided fuel cost of the net energy (kWh) delivered to the Company. With the exception of the Energy Charge, all other applicable standard rate charges shall apply.


Summer Season: $0.0538/kWh

Winter Season: $0.0493/kWh

Rebates Offered
No

Interconnection & taps

Approval Req To Install
Yes
Line Taps Allowed
No
Load Taps Allowed
No
Automatic Transformer Upgrade Size
0

System size & offset

System Size Restrictions
100
System Size Restriction Type
AC kW
System Size Battery Included
No
System Size Includes Existing Systems
No
Offset Type
Combination
Offset Value
100
Offset Calculation Basis
Historical
Offset Calculation Period
12
Industry Standard Watts Sqft
2
Offset Calc Tool
Historical Usage

Metering & disconnect

Production Meter Required
No
AC Disconnect Required
Yes
AC Disconnect Labeling
Utility Disconnect Switch

Plans & docs

Site Plan Reqs

Standard

SLD Reqs

Standard -

  • The diagram must clearly show the routing and connection(s) of all conductors, i.e. line one, line two, neutral and ground) in the path form the grid-tie inverter to the load panel and include references to the Company’s Point of Service
Electric Service Reqs

Net metering interconnection equipment, such as power inverters, must be IEEE 1547 compliant as certified by UL 1741 testing in order to be approved by Liberty for Net Metering installations.

Install Reqs

AC Disconnect Required MUST BE ACCESSIBLE 24/7

Placards

All placards need to be black with white lettering.


Please review the placard examples uploaded to the files.

Electrical Stamp Required
No
Equipment Approvals
California Energy Commission
Meter Num Req SLD 3LD
No
ESID Num Req SLD 3LD
No
Electrical Diagram Notes
  • The checklist MUST be completed to ensure commissioning will be accomplished.
  • Please complete and sign the post certificate.
  • Ensure the installer has the Net Metering Installer Requirements on hand during installation.
  • If the meter is in the backyard with dogs at any point and time, the disconnect will have to move outside the fence. NO EXCEPTIONS. 
  • If the meter is in a locked fenced in area, the disconnect will have to move outside the fence or a combination lock will need to be installed and code provided. NO EXCEPTIONS.
Rate Schedule Link
link

Other details

Revision Required
Yes
Compiled from public records, 2026. Tariffs and interconnection rules change; verify with Liberty Utilities (MO) before you rely on this. The useful move: if an installer says you need a main panel upgrade, ask how these tap and interconnection policies were considered first.