Central Electric (NC)

North Carolina Utility Interconnection & net metering rules

Spot something wrong?

Tariffs and interconnection rules move often. If something here is out of date or missing, tell us and we'll fix it.

Report a correction
Net Metering AllowedYes
NEM TypeMonthly
Line Taps AllowedNo
Load Taps AllowedNo
AC Disconnect RequiredYes

Net metering & export

Net Metering Allowed
Yes
NEM Type
Monthly
Post Solar Billing Method
Net Metering
Solar Export Type
Avoided Cost
Solar Export Rate Approx
0.0525
Net Excess Generation Notes

"There are two(2) Riders but their rates/requirements are similar. The SMALL CONSUMER-OWNED GENERATOR RIDER is for systems where The nameplate rating of the Renewable Generation is the lesser of the consumer’s historical maximum 15- minute integrated demand or 10 kW. The PURCHASED POWER RIDER is for systems less than 500kW.


Consumers generating power from a renewable resource, as defined in this Rider, shall be billed for all energy and kW demand, if applicable, that is delivered by the Cooperative under the rate schedule the consumer receives service, plus any applicable riders, during the billing month.

The consumer will receive credits for all excess energy delivered to the Cooperative’s system during the billing month at the rate of 5.25 cents ($0.0525) per kWh and is subject to change based upon the Cooperative’s estimated avoided cost of wholesale purchased power.


The consumer’s service may be metered with: (a) a single, bi-directional meter, which records independently the flow of electricity in each direction through the meter; or (b) at the Cooperative’s option, two meters, equipped to prevent reverse registration, one which will measure the energy delivered by the Cooperative to the consumer, and the other which will measure the energy delivered by the consumer to the Cooperative. The Cooperative shall have the right to install special metering and load research devices on the consumer’s equipment and the right to use the consumer’s telephone line for communication with the Cooperative’s and the consumer’s equipment. "

Rebates Offered
No
Deregulated
No

Interconnection & taps

Approval Req To Install
Yes
Line Taps Allowed
No
Load Taps Allowed
No
Automatic Transformer Upgrade Size
0

System size & offset

System Size Restrictions
10
System Size Restriction Type
AC kW
System Size Battery Included
No
System Size Includes Existing Systems
No
Offset Type
No Restrictions
Offset Value
0
Offset Calculation Period
0
Industry Standard Watts Sqft
2
System Offset Notes

10kW AC is max

Offset Calc Tool
PV Watts

Metering & disconnect

Production Meter Required
No
AC Disconnect Required
Yes
Allowed Meter Adapter
None

Plans & docs

Site Plan Reqs

Member shall install a manual load-break disconnect switch with a clear visible indication of switch position between Company's electric system and Member's Generator. It is preferred the Isolation Device be within five feet (5’) of the meter base

SLD Reqs

No Production Meter Required

Placards

Member will install a permanent warning label in a conspicuous place in close proximity to the electric meter or on the meter base to notify Company personnel that there is a generator installed on the load side of the meter. The warning label shall not be placed in a location that would interfere with the ability of Company personnel to read the electric meter. Member shall also place a warning label on the Isolation Device. The warning labels must be in place before the Generator can be interconnected with Company's system.

Website
link
Phone
(800) 446-7752

Other details

Revision Required
Yes
Mod Swap Requires Planset
Yes
Compiled from public records, 2026. Tariffs and interconnection rules change; verify with Central Electric (NC) before you rely on this. The useful move: if an installer says you need a main panel upgrade, ask how these tap and interconnection policies were considered first.