NEM TypeMonthly
Line Taps AllowedNo
Load Taps AllowedNo

Net metering & export

NEM Type
Monthly
Post Solar Billing Method
Export Rate
Net Excess Generation Notes

We currently offer two solar rates:

Sell All - Requires the installation of a separate service. All energy generated is then metered and purchased by HEMC at 4.4¢ kWh.

Sell Excess - Electricity generated by the solar panels is consumed by the house first, and any excess/leftover electricity is purchased by Haywood EMC at 4.4¢ kWh.

Each month your bill will include a line item named “Renewable Generation Credit” listing the amount purchased back by Haywood EMC.

Rebates Offered
No
Deregulated
No

Interconnection & taps

Approval Req To Install
Yes
Line Taps Allowed
No
Load Taps Allowed
No
Automatic Transformer Upgrade Size
0

System size & offset

System Size Restrictions
100
System Size Restriction Type
DC kW
System Size Battery Included
No
System Size Includes Existing Systems
No
Offset Type
No Restrictions
Offset Value
0
Offset Calculation Period
0
Industry Standard Watts Sqft
2
System Offset Notes


Metering & disconnect

Production Meter Required
No
Production Meter Position
N/A
Production Meter Labeling
N/A
Allowed Meter Adapter
None

Plans & docs

Site Plan Reqs


SLD Reqs


Electric Service Reqs


Equipment Approvals
California Energy Commission
Meter Num Req SLD 3LD
No
ESID Num Req SLD 3LD
No
Rate Schedule Link
link
Website
link
Phone
(800) 951-6088

Other details

Revision Required
Yes
Mod Swap Requires Planset
Yes
Compiled from public records, 2026. Tariffs and interconnection rules change; verify with Haywood EMC before you rely on this. The useful move: if an installer says you need a main panel upgrade, ask how these tap and interconnection policies were considered first.