El Paso Electric (NM)
Net Metering Allowed1
Supply Side Taps Allowed1
Line Taps Allowed1
Load Taps Allowed1
AC Disconnect RequiredYes
Net metering & export
- Net Metering Allowed
- 1
- Post Solar Billing Method
- Net Metering
- Rebates Offered
- 0
- Allows Standby
- 0
Interconnection & taps
- Approval Req To Install
- Yes
- Interconnection Level
- 2
- Supply Side Taps Allowed
- 1
- Line Taps Allowed
- 1
- Load Taps Allowed
- 1
- Automatic Transformer Upgrade Size
- 0
- Meter Aggregation Allowed
- 0
System size & offset
- System Size Restrictions
- 0
- System Size Restriction Type
- No Restrictions
- System Size Battery Included
- 0
- System Size Includes Existing Systems
- 0
- Offset Type
- Percentage
- Offset Value
- 120
- Offset Calculation Basis
- Historical
- Offset Calculation Period
- 12
- Industry Standard Watts Sqft
- 2
- System Offset Notes
120% of customer's annual consumption to be qualified for NET METERING
- Offset Calc Tool
- Historical Usage
Metering & disconnect
- Production Meter Required
- Yes
- Production Meter Position
- Inv-PM-Disco-POI
- Production Meter Labeling
- Production Meter
- AC Disconnect Required
- Yes
- AC Disconnect Labeling
- Visible Lockable Labeled Disconnect
- Allowed Meter Adapter
- None
Plans & docs
- SLD Reqs
Relay Meter Orientation = Over/Under
- Ubill holder must be listed on the SLD
- Inv to the top of PM, bottom of PM to AC Disco > MSP > bottom of UM.
- Utility will install one Production Meter (PM) and one Utility Bidirectional Meter (UM).
- Existing and new solar installations must be metered by the same PM.
- See "One line requirements and SLD sample.pdf" in Files section of this page.
- The breaker rating specified on the SLD must match the installed breaker.
- Show sizing table for wires between AC Disconnect and PM, and between PM and MSP.
- Load calcs required on all projects
- Section 230.67 of the new 2020 NEC requires the installation of a surge-protective device (SPD) for all dwelling unit service entrances. New and replaced electrical equipment and systems must incorporate Type 1 or Type 2 SPDs. Type 1 surge protective devices can be installed before the main disconnect in the load center, at the meter enclosure or on the load side of the main circuit breaker. Type 2 surge protective devices can only be installed on the load side of the main disconnect, attached directly to a circuit breaker. Often, new construction will install Type 1 surge protectors, while renovations will install Type 2 surge protectors, but both types will satisfy the new requirements.
- As of July 1, 2021, this state uses the 2020 NEC. See "Surge Protection and NEC 2020" in Files section of this page.
Existing Systems
- Existing and new solar installations must be metered by the same PM.
- The one-line MUST show how much the current system is producing and how much the addition will produce as well as the total expected annual production.
- The one-line MUST show the sizes in AC and DC for both, existing and additional equipment. ie. Existing: 1x Solar Edge SE3000= 3.0 kW AC, 10 X 300w Panasonic X = 3.0 kW DC, NEW: 1X Solar Edge SE3000...
- Show kW-DC size of existing, new and combined systems. See "System Size example" in Files section of this page.
- Electric Service Reqs
- If existing meter is to be opened (Line tap or MBE), existing meter must be rated for 200A or more
- Must have 3ft clearance in from of main panel, we will need to relocate
- /\ /\ If existing UG service, we will need a meter spot to grandfather existing location
- Bubble meters not permitted, must upgrade if existing bubble meter or under 100A service
- Electrical Review Team \/ \/ \/ \/
- Meter needs to be 80ft or closer from utility pole (if closest point on home is not within 80ft, we need a utility engineer to give the okay on the service drop distance to be left as is or may be required to install a meter pole closer to their utility pole)
- Meter cannot be under a porch nor service line crossing a roof less than 8ft in height (service line to roof) or 4ft in length
- Weatherhead is to be 36 inches from roofline
- Middle of meter bubble must be minimum 4ft, max 5ft 6inches
- No embedded meters allowed (if opening meter, would need to bring this out)
- In the event that there is a tree in the path of where the service line will be running through (overhead), this will need to be trimmed prior to the utility energizing the MPU
- Electrical Stamp Required
- 0
- Meter Num Req SLD 3LD
- 0
- ESID Num Req SLD 3LD
- 0
- Website
- link
- Phone
- (915) 872-4595
Other details
- Restrict Inspection
- 0
- Address ID
- 146328
- Express Planset Eligible
- No