Amherst Utilities Department
Spot something wrong?
Tariffs and interconnection rules move often. If something here is out of date or missing, tell us and we'll fix it.
Report a correction Net Metering AllowedNo
Line Taps AllowedNo
Load Taps AllowedNo
Net metering & export
- Net Metering Allowed
- No
- TOU Utility
- No
- Post Solar Billing Method
- Export Rate
- Solar Export Type
- Fixed kWh
- Solar Export Rate
- 0.0931
- Solar Export Value Notes
- Updates annually
- Net Excess Generation Notes
The net monthly payment to Customer for power supplied to Utility by the small power production facility shall be equal to the kilowatt-hours of energy supplied by the small power production facility multiplied by Utility's average power supply costs for the calendar year immediately preceding the month in which the power is delivered to Utility by the small power production facility. Annual true up in January.
- Rebates Offered
- No
Interconnection & taps
- Approval Req To Install
- Yes
- Line Taps Allowed
- No
- Load Taps Allowed
- No
- Automatic Transformer Upgrade Size
- 0
System size & offset
- System Size Battery Included
- No
- System Size Includes Existing Systems
- No
- Offset Value
- 0
- Offset Calculation Period
- 0
- Industry Standard Watts Sqft
- 2
- System Offset Notes
- Maximum system size: 10.00 kW
- Limited to 100% of the customer's historical peak load in kW
Metering & disconnect
- Production Meter Required
- No
- Production Meter Position
- N/A
- Production Meter Labeling
- N/A
- Allowed Meter Adapter
- None
Plans & docs
- Site Plan Reqs
- AC Disconnect must be accessible to the utility 24/7
- Website
- link
- Phone
- (440) 988-4224