Washington Electric Cooperative (OH)

Ohio Utility Interconnection & net metering rules

Spot something wrong?

Tariffs and interconnection rules move often. If something here is out of date or missing, tell us and we'll fix it.

Report a correction
Line Taps AllowedNo
Load Taps AllowedNo
AC Disconnect RequiredYes

Net metering & export

TOU Utility
No
Post Solar Billing Method
Export Rate
Solar Export Type
Avoided Cost
Solar Export Rate Approx
0.077
Solar Export Value Notes
Should the co-generation credit exceed the current month’s Distribution Energy Charges and Generation & Transmission Charges, then the remaining balance is forwarded on to be used on future m
Rebates Offered
No
Deregulated
Yes

Interconnection & taps

Approval Req To Install
Yes
Line Taps Allowed
No
Load Taps Allowed
No
Automatic Transformer Upgrade Size
0
Meter Aggregation Allowed
No

System size & offset

System Size Restrictions
25
System Size Restriction Type
DC kW
System Size Battery Included
No
System Size Includes Existing Systems
No
Offset Type
Combination
Offset Value
100
Offset Calculation Basis
Historical
Offset Calculation Period
12
Industry Standard Watts Sqft
2
System Offset Notes

25 kW or 100% offset whichever is less.

Offset Calc Tool
Historical Usage

Metering & disconnect

Production Meter Required
No
AC Disconnect Required
Yes
AC Disconnect Labeling
Visible Lockable Labeled Disconnect
Allowed Meter Adapter
None

Plans & docs

Site Plan Reqs

Must show location of the following:

  • inverter
  • PV panels
  • meter
  • accessible disconnect switch
SLD Reqs

Standard

Electric Service Reqs

A disconnect switch to isolate the DR equipment is required. The switch must be clearly labeled as a DR disconnect switch


PV W/ BATTERY:

If the customer connects a backup generator directly to the customer’s wiring to serve any load on the customer’s site, it shall utilize a double-throw transfer switch in order to ensure that no power is fed back onto the Cooperative’s distribution system. This is a critical safety requirement.

Equipment Approvals
California Energy Commission
ESID Num Req SLD 3LD
No
Rate Schedule Link
link
Website
link
Phone
(740) 885-5941

Other details

Revision Required
Yes
Mod Swap Requires Planset
Yes