OK - Verdigris Valley Electric Coop
Spot something wrong?
Tariffs and interconnection rules move often. If something here is out of date or missing, tell us and we'll fix it.
Report a correctionNet metering & export
- Net Metering Allowed
- Yes
- NEM Type
- Monthly
- TOU Utility
- No
- Post Solar Billing Method
- Net Metering
- Net Excess Generation Notes
When the energy supplied by the member exceeds the energy supplied by the Cooperative during a billing period, the monthly charge and/or minimum bill of the retail rate schedule shall be billed by the Cooperative in addition to the monthly metering charge, and the excess energy shall be purchased at the Cooperative’s Power Supplier’s avoided cost as determined by the Cooperative’s Power Supplier as a credit on the member's next bill.
Avoided cost = $0.02 - $0.04 / kWh (changes monthly and/or as needed)
- Rebates Offered
- No
- Deregulated
- No
- Allows Standby
- No
Interconnection & taps
- Approval Req To Install
- Yes
- Line Taps Allowed
- No
- Load Taps Allowed
- No
- Automatic Transformer Upgrade Size
- 0
System size & offset
- System Size Restrictions
- 125
- System Size Restriction Type
- Percent
- System Size Battery Included
- No
- System Size Includes Existing Systems
- No
- Offset Value
- 0
- Offset Calculation Period
- 0
- Industry Standard Watts Sqft
- 2
- Inverter Oversize Restrictions
- No
- System Offset Notes
For Net Metering System:
- 25 kW AC or 125% of the customer's historical usage (whichever is less)
System can be sized over 25 kW AC but will not be eligible for Net Metering = not recommended
- Offset Calc Tool
- Historical Usage
Metering & disconnect
- Production Meter Required
- No
- Production Meter Position
- N/A
- Production Meter Labeling
- N/A
- AC Disconnect Required
- Yes
- AC Disconnect Labeling
- Utility Disconnect Switch
Plans & docs
- Equipment Approvals
- California Energy Commission
- Meter Num Req SLD 3LD
- Yes
- ESID Num Req SLD 3LD
- Yes
- Rate Schedule Link
- link
- Website
- link
- Phone
- (918) 371-2584
Other details
- Revision Required
- Yes
- Mod Swap Requires Planset
- Yes