Coos-Curry Electric Coop, Inc

Oregon Utility Interconnection & net metering rules
Net Metering Allowed1
NEM TypeAnnual
Line Taps Allowed0
Load Taps Allowed0

Net metering & export

Net Metering Allowed
1
NEM Type
Annual
Post Solar Billing Method
Net Metering
Solar Export Type
Avoided Cost
Net Excess Generation Notes

* During each billing period, CCEC will supply energy from the grid when a net metered location is using more power than their onsite generation can provide. When the onsite generation is producing more energy than is needed the excess is sent back to the power grid. Each billing period the energy sent back is subtracted from the energy supplied by CCEC and the member is only charged the difference.

* If the amount of energy generated is greater than the amount of energy delivered, the difference in kilowatt-hours shall be defined as excess energy. Excess energy shall be banked and used to offset future consumption. Once a year, if the credit is substantial, the banked excess energy will be credited to the member’s account at the avoided cost rate. 

Rebates Offered
0

Interconnection & taps

Approval Req To Install
Yes
Interconnection Level
3
Line Taps Allowed
0
Load Taps Allowed
0
Automatic Transformer Upgrade Size
0
Meter Aggregation Allowed
0

System size & offset

System Size Restrictions
25
System Size Restriction Type
DC kW
System Size Battery Included
0
System Size Includes Existing Systems
0
Offset Type
Combination
Offset Value
100
Offset Calculation Basis
Historical
Offset Calculation Period
12
Industry Standard Watts Sqft
2
System Offset Notes

The distributed generation facility is intended to primarily offset part or all of the member's own electrical requirements.

Maximum system size is 25 kW DC

Offset Calc Tool
Historical Usage

Metering & disconnect

Production Meter Required
No
Production Meter Position
N/A
Production Meter Labeling
N/A
Allowed Meter Adapter
None

Plans & docs

Equipment Approvals
California Energy Commission
Rate Schedule Link
link
Website
link

Other details

Restrict Inspection
0
Revision Required
1
Address ID
1229742
Express Planset Eligible
Yes