Douglas Electric Cooperative

Oregon Utility Interconnection & net metering rules
Net Metering Allowed1
NEM TypeAnnual
Line Taps Allowed0
Load Taps Allowed0

Net metering & export

Net Metering Allowed
1
NEM Type
Annual
Post Solar Billing Method
Net Metering
Net Excess Generation Notes

At the annual true-up, at the end of the customer’s April billing cycle, any remaining unused credit from any excess generation shall be valued at the avoided cost, and at the customer-generator’s election, be returned to the customer-generator or granted to the Cooperative’s low-income energy assistance program.

Rebates Offered
0
Deregulated
0

Interconnection & taps

Approval Req To Install
Yes
Interconnection Level
3
Line Taps Allowed
0
Load Taps Allowed
0
Automatic Transformer Upgrade Size
0
Meter Aggregation Allowed
1

System size & offset

System Size Restrictions
25
System Size Restriction Type
AC kW
System Size Battery Included
0
System Size Includes Existing Systems
0
Offset Type
No Restrictions
Offset Value
0
Offset Calculation Period
0
Industry Standard Watts Sqft
2
System Offset Notes

Nameplate generating capacity of not more than twenty-five (25) kilowatts per meter

Offset Calc Tool
PV Watts

Metering & disconnect

Production Meter Required
No
Production Meter Position
N/A
Production Meter Labeling
N/A
Allowed Meter Adapter
None

Plans & docs

Site Plan Reqs
  • AC Disco must be next to POI/Utility meter
SLD Reqs

See SLD Sample

Install Reqs

Customer-generator shall furnish and install, on its side of the meter, a disconnecting device capable of fully disconnecting and isolating the net metering facility from the Cooperative’s electric supply system. The disconnecting device shall be located adjacent to the Cooperative’s bi-directional metering equipment and shall be of the visible break type in a metal enclosure that can be secured by a Cooperative owned padlock.

Equipment Approvals
California Energy Commission
Rate Schedule Link
link
Website
link
Phone
(541) 673-6616

Other details

Restrict Inspection
0
Address ID
283964
Express Planset Eligible
Yes
Compiled from public records, 2026. Tariffs and interconnection rules change; verify with Douglas Electric Cooperative before you rely on this. The useful move: if an installer says you need a main panel upgrade, ask how these tap and interconnection policies were considered first.