Salem Electric (OR)
Net metering & export
- Net Metering Allowed
- 1
- NEM Type
- Annual
- Post Solar Billing Method
- Net Metering
- Net Excess Generation Notes
"Effective October 1, 2019, each monthly billing period Salem Electric will charge a member-generator the monthly facilities charge and all applicable charges for the net electricity that Salem Electric delivered. If in a monthly billing period a member-generator has supplied to Salem Electric more electricity than Salem Electric has delivered to the member-generator, Salem Electric will apply the excess kWhs as a cumulative credit to the member-generator’s monthly bill. Salem Electric will apply such credit at the avoided cost rate for each component on the bill that uses kWhs as the billing determinant.
Systems installed prior to October 1, 2019, will be paid on an annual true-up through April 1, 2040. For the billing cycle ending in March of each year, or at any other time the member discontinues service at the net-metered account, if any unused credits accumulated during the previous 12 months remain, Salem Electric will pay the member-generator an amount equal to the unused credited kWhs times the average wholesale price of power purchased by Salem Electric. Modifications of existing net-metered PV systems that require a new net-metering agreement immediately revokes the application of annual true-up credit, changing the credit determination to a monthly true up credit. The annual true up is non-transferrable. After April 2040, all net-metered PV systems will have a monthly true up.
"
- Rebates Offered
- 1
Interconnection & taps
- Approval Req To Install
- Yes
- Interconnection Level
- 3
- Line Taps Allowed
- 0
- Load Taps Allowed
- 0
- Automatic Transformer Upgrade Size
- 0
System size & offset
- System Size Battery Included
- 0
- System Size Includes Existing Systems
- 0
- Offset Value
- 0
- Offset Calculation Period
- 0
- Industry Standard Watts Sqft
- 2
- System Offset Notes
Incentives are available for qualifying photovoltaic (PV) systems that are net metered, do not exceed a generation capacity of 25kW, and comply with SE’s Net Metering Policy.
Metering & disconnect
- Meter Spot Process
Temporary Disconnect Reconnect Process (TDR) As long as it's during business hours it's free. If we have to reconnect after hours, there is an overtime charge that can range from $250-500. If the work requires an electrical inspection, we will not reconnect until it's inspected or unless a licensed electrician signs a reconnect form.
TDR - Who to
TDR - Applications/Documents Req N/A
TDR - ETA of notice required for request
TDR - Who can schedule? Does not matter
TDR - ETA of Utility Scheduling TDR
- Allowed Meter Adapter
- None
Plans & docs
- SLD Reqs
See SLD Sample
No Production Meter Required
- Website
- link
- Phone
- (503) 362-3601
Other details
- Restrict Inspection
- 0
- Address ID
- 607762
- Express Planset Eligible
- Yes