AEP Texas North Company

Texas Utility Interconnection & net metering rules

Spot something wrong?

Tariffs and interconnection rules move often. If something here is out of date or missing, tell us and we'll fix it.

Report a correction
Line Taps AllowedYes
Load Taps AllowedYes
MPU Rules<p>overhead services are required to go through the soffit n
AC Disconnect RequiredYes

Net metering & export

Post Solar Billing Method
Export Rate
Rebates Offered
No
Allows Standby
No

Interconnection & taps

Approval Req To Install
Yes
Line Taps Allowed
Yes
Load Taps Allowed
Yes
Tap Criteria

Taps

  • Piercing Tap - allowed
  • Supply Side Tap - allowed
  • Line Side Tap - allowed
  • Load (breaker) Tap - allowed
  • No connections directly to the meter
  • Line side tap conductors must end in a breaker or fuses not in mlo lugs in the panel.
MPU Rules

overhead services are required to go through the soffit now and exceed roof deck height at least 2 feet.

Automatic Transformer Upgrade Size
0

System size & offset

System Size Restrictions
0
System Size Restriction Type
No Restrictions
System Size Battery Included
No
System Size Includes Existing Systems
No
Offset Type
No Restrictions
Offset Value
0
Offset Calculation Period
0
Industry Standard Watts Sqft
2
System Offset Notes

System Sizing (Incentive Projects ONLY)

- To be eligible for an incentive payment, the output of a solar system (in PV Watts) must be at least 80% of estimated annual usage. Installations which do not meet the minimum performance threshold will not receive an incentive. Prorated incentives are not available.

Offset Calc Tool
PV Watts

Metering & disconnect

Production Meter Required
No
Production Meter Position
N/A
Production Meter Labeling
N/A
AC Disconnect Required
Yes
Allowed Meter Adapter
None,None

Plans & docs

Site Plan Reqs
  • EXTERIOR EMERGENCY DISCONNECT REQUIRED ON ALL PROJECTS PER NEC 230.85
  • AEP only requests to see where the AC Disconnect is located in relation to the existing meter.
  • AC Disconnect is required to be within 3FT of the AEP Meter.
  • Please label the AC Disconnect as fused/ non-fused
  • We need a minimum 2" clearance on each side all electrical equipment.
SLD Reqs

ALL JOBS

  • PV Panels -> Inverter -> AC Disconnect -> MSP -> Utility (AEP) Meter
  • Split PV Systems not allowed. 
  • Please label the AC Disconnect as fused/ non-fused
  • 200A EXTERIOR EMERGENCY DISCONNECT REQUIRED ON ALL PROJECTS PER NEC 230.85. DISCONNECT MUST SHUT OFF ENTIRE HOME (MBE WILL SUFFICE)

Battery Jobs

  • DISONNECT REQUIRED BETWEEN MID AND POI
  • PV Panels -> Inverter -> AC Disconnect -> MID -> AC Disco -> MSP/UM
  • Battery system label required on the meter..

Existing Systems

  • New and existing systems must connect behind a single AC disconnect.
  • Split PV Systems not allowed. 
Electric Service Reqs
  • SERVICE MUST BE 200A MINIMUM TO INTERCONNECT SOLAR. MPU IF LESS THAN 200A
  • overhead services are required to go through the soffit now and exceed roof deck height at least 2 feet.
Install Reqs


Placards
  • AEP has own set of placards
  • Placards required from when AC disconnect not within LOS of utility meter. supplemental Terms & Conditions must be added to the agreement
  • Line Side Tap require a placard installed in the utility meter.
Label Page Notes


Electrical Diagram Notes

All Jobs [visible, lockable, labeled, utility-accessible AC disconnect located within 3FT of the utility meter // Inverter UL1741 SB certified]

Rate Schedule Link
link
Website
link
Phone
(877) 373-4858
Compiled from public records, 2026. Tariffs and interconnection rules change; verify with AEP Texas North Company before you rely on this. The useful move: if an installer says you need a main panel upgrade, ask how these tap and interconnection policies were considered first.