Net Metering AllowedYes
NEM TypeMonthly
Line Taps AllowedNo
Load Taps AllowedNo

Net metering & export

Net Metering Allowed
Yes
NEM Type
Monthly
Post Solar Billing Method
Net Metering
Net Excess Generation Notes

If Customer’s electric installation produces excess electricity, City shall pay Customer for excess electricity at the City’s “avoided cost”. Customer’s excess electricity shall be carried over month to month as a credit; but, Customer shall be paid a refund when service is either discontinued or at the end of the City’s fiscal year. Credits shall not be carried over into another fiscal year or be transferrable.

Rebates Offered
No

Interconnection & taps

Approval Req To Install
Yes
Line Taps Allowed
No
Load Taps Allowed
No
Automatic Transformer Upgrade Size
0
Meter Aggregation Allowed
No

System size & offset

System Size Restrictions
20
System Size Restriction Type
DC kW
System Size Battery Included
No
System Size Includes Existing Systems
No
Offset Type
No Restrictions
Offset Value
0
Offset Calculation Period
0
Industry Standard Watts Sqft
2

Metering & disconnect

Production Meter Required
No
Production Meter Position
N/A
Production Meter Labeling
N/A
Allowed Meter Adapter
None