DME - Denton Municipal Electric

Texas Utility Interconnection & net metering rules

Spot something wrong?

Tariffs and interconnection rules move often. If something here is out of date or missing, tell us and we'll fix it.

Report a correction
Net Metering AllowedYes
NEM TypeMonthly
Line Taps AllowedYes
Load Taps AllowedYes

Net metering & export

Net Metering Allowed
Yes
NEM Type
Monthly
Post Solar Billing Method
Net Metering
Rebates Offered
No
Deregulated
No
Allows Standby
No

Interconnection & taps

Approval Req To Install
No
Line Taps Allowed
Yes
Load Taps Allowed
Yes
Tap Criteria

Taps need to be in a tap box. (Not allowed in MSP)

Automatic Transformer Upgrade Size
0

System size & offset

System Size Restrictions
0
System Size Restriction Type
No Restrictions
System Size Battery Included
No
System Size Includes Existing Systems
No
Offset Type
No Restrictions
Offset Value
0
Offset Calculation Period
0
Industry Standard Watts Sqft
2

Metering & disconnect

Production Meter Required
No
Production Meter Position
N/A
Production Meter Labeling
N/A
Allowed Meter Adapter
None

Plans & docs

Site Plan Reqs

Site electrical with configuration and physical locations of DG facility, meter and disconnect

Do not include CEC-AC on a summary page

SLD Reqs

REQUIRED Per Utility: One-line and a Three-line Electrical Schematic Drawing signed and stamped by a Texas Licensed Electrical Professional Engineer

Should Include the following:

Customer's name

Engineer's name

Number of units and how units are connected

What kind of conductor (must be labeled) i.e: live, neutral, ground and size

Size of breaker

Size of inverter

Rating of sub panel

Line side tap conductors must end in a breaker or fuses not in mlo lugs in the panel.

Needs to show how the neutral and ground lines are bonded inside the main service panel.

Structural letter is needed with calculations.

SLD needs to show two 120Vac phases, one neutral conductor and one grounding electrode conductor. SLD also needs to show, Ground/Neutral bonding at GEC.

Electric Service Reqs

**Taps**

The City of Denton prohibits double lugging or pierce line taps for interconnections. Line side taps are only allowed through a junction box." (.

**System Sizing**

 Minimum PV install of 3 kW.

 Minimum battery install of 3 kW or reasonably sized to PV install

Install Reqs

After Passed Inspection with City - please have the system turned on for DME testing.

Electrical Stamp Required
Yes
Rate Schedule Link
link
Website
link
Phone
(940) 349-8700
Compiled from public records, 2026. Tariffs and interconnection rules change; verify with DME - Denton Municipal Electric before you rely on this. The useful move: if an installer says you need a main panel upgrade, ask how these tap and interconnection policies were considered first.