Net Metering AllowedYes
Supply Side Taps AllowedYes
Line Taps AllowedYes
Load Taps AllowedYes
AC Disconnect RequiredYes

Net metering & export

Net Metering Allowed
Yes
TOU Utility
No
Post Solar Billing Method
Net Metering
Rebates Offered
No
Deregulated
No
Allows Standby
No

Interconnection & taps

Approval Req To Install
Yes
Supply Side Taps Allowed
Yes
Line Taps Allowed
Yes
Load Taps Allowed
Yes
Automatic Transformer Upgrade Size
0

System size & offset

System Size Restrictions
0
System Size Restriction Type
No Restrictions
System Size Battery Included
No
System Size Includes Existing Systems
No
Offset Type
No Restrictions
Offset Value
0
Offset Calculation Period
0
Industry Standard Watts Sqft
2

Metering & disconnect

Production Meter Required
No
Production Meter Position
N/A
Production Meter Labeling
N/A
AC Disconnect Required
Yes
AC Disconnect Labeling
Visible Lockable Labeled Disconnect
Allowed Meter Adapter
Tesla Backup Switch

Plans & docs

Site Plan Reqs


SLD Reqs

Line side taps are allowed. Be sure to use Fused AC Disconnect.

Electrical Stamp Required
No
Meter Num Req SLD 3LD
No
ESID Num Req SLD 3LD
No
Website
www.grayson-collin.coop
Phone
(903) 482-7100

Other details

Revision Required
No