SPEC - Southern Plains Electric Cooperative
Net metering & export
- Net Metering Allowed
- 1
- NEM Type
- Monthly
- TOU Utility
- 0
- Post Solar Billing Method
- Net Metering
- Solar Export Type
- Fixed kWh
- Solar Export Rate
- 0.81861
- Net Excess Generation Notes
Net-metering members are defined as members who have placed a type of distributed generation which is no greater than 50 kW behind the Cooperative’s meter. A member qualifying for this rate will receive credit in kWh
generated against kWh consumed in one billing period. Kilowatt-hour credits will only offset up to the amount of kWh consumed in each billing period. All other applicable charges will be billed
- Rebates Offered
- 0
- Deregulated
- 0
Interconnection & taps
- Approval Req To Install
- Yes
- Interconnection Level
- 3
- Line Taps Allowed
- 0
- Load Taps Allowed
- 0
- Automatic Transformer Upgrade Size
- 0
System size & offset
- System Size Battery Included
- 0
- System Size Includes Existing Systems
- 0
- Offset Value
- 0
- Offset Calculation Period
- 0
- Industry Standard Watts Sqft
- 2
- System Offset Notes
Up to 50kW
Metering & disconnect
- Production Meter Required
- No
- Production Meter Position
- N/A
- Production Meter Labeling
- N/A
- Meter Spot Process
Temporary Disconnect Reconnect Process (TDR) The installer can call in to our member service reps and request a temporary disconnect any time.
TDR - Who to Contact Member Service
TDR - Applications/Documents Req
TDR - ETA of notice required for request 24 hours
TDR - Who can schedule? Does not matter
TDR - ETA of Utility Scheduling TDR
- Allowed Meter Adapter
- None
Plans & docs
- Site Plan Reqs
Plans Sample Attached
- SLD Reqs
Visible, Lockable, Labeled AC Disconnect to be located within 10' of utility meter.
- Placards
Placard to be placed on meter showing all equipment on the home
- Equipment Approvals
- California Energy Commission
- Website
- link
Other details
- Restrict Inspection
- 0
- Address ID
- 378287
- Express Planset Eligible
- Yes