City of Ephraim

Utah Utility Interconnection & net metering rules

Spot something wrong?

Tariffs and interconnection rules move often. If something here is out of date or missing, tell us and we'll fix it.

Report a correction
Net Metering AllowedYes
NEM TypeMonthly
Line Taps AllowedNo
Load Taps AllowedNo

Net metering & export

Net Metering Allowed
Yes
NEM Type
Monthly
TOU Utility
No
Post Solar Billing Method
Net Metering
Net Excess Generation Notes

If the electricity generated by the Customer’s System exceeds the Customer’s consumption, and the Customer’s excess electricity is distributed back to the City during the billing period, then the Customer shall still be billed for the customer service charge(s) paid by other customers of the City in the same rate class as Customer, however, Customer shall be credited for the net excess kilowatt-hours generated during the billing period at a wholesale rate set forth in the City’s fee schedule, which may be amended from time to time at the sole discretion of the City. Any credit earned by the Customer shall appear on Customer’s bill for the following billing period. On April 30th of each calendar year, any remaining unused kilowatt-hour credit accumulated during the previous year shall be granted to the City without any compensation to Customer.

Rebates Offered
No
Deregulated
No

Interconnection & taps

Approval Req To Install
Yes
Line Taps Allowed
No
Load Taps Allowed
No
Automatic Transformer Upgrade Size
0
Meter Aggregation Allowed
No

System size & offset

System Size Restrictions
5
System Size Restriction Type
DC kW
System Size Battery Included
No
System Size Includes Existing Systems
No
Offset Value
0
Offset Calculation Period
0
Industry Standard Watts Sqft
2
System Offset Notes

Maximum 5 kW for residential; 15 kW for commercial

Metering & disconnect

Production Meter Required
No
Production Meter Position
N/A
Production Meter Labeling
N/A
Allowed Meter Adapter
None

Plans & docs

Equipment Approvals
California Energy Commission
Website
link
Phone
(435) 283-4631
Compiled from public records, 2026. Tariffs and interconnection rules change; verify with City of Ephraim before you rely on this. The useful move: if an installer says you need a main panel upgrade, ask how these tap and interconnection policies were considered first.