Provo Power

Utah Utility Interconnection & net metering rules

Spot something wrong?

Tariffs and interconnection rules move often. If something here is out of date or missing, tell us and we'll fix it.

Report a correction
Net Metering AllowedNo
NEM TypeMonthly
Line Taps AllowedNo
Load Taps AllowedNo

Net metering & export

Net Metering Allowed
No
NEM Type
Monthly
TOU Utility
No
Post Solar Billing Method
Export Rate
Solar Export Type
Fixed kWh
Solar Export Rate
0.067
Solar Export Value Notes
Rate changes every year (March)
Net Excess Generation Notes

Excess energy (not used) generated will be exported back to the grid and will be purchased at a fixed cost (as of 2023: $0.067 / kWh).


On February 28th of each calendar year, any remaining unused credit accumulated during the previous year shall be granted to Provo City Power, without any compensation to the Customer.

Rebates Offered
No
Deregulated
No

Interconnection & taps

Approval Req To Install
Yes
Line Taps Allowed
No
Load Taps Allowed
No
Automatic Transformer Upgrade Size
0

System size & offset

System Size Restrictions
0
System Size Restriction Type
No Restrictions
System Size Battery Included
No
System Size Includes Existing Systems
No
Offset Type
No Restrictions
Offset Value
0
Offset Calculation Period
0
Industry Standard Watts Sqft
2
Offset Calc Tool
N/A

Metering & disconnect

Production Meter Required
Yes
Allowed Meter Adapter
None

Plans & docs

SLD Reqs

PV Panels -> (Combiner Box if required) -> Inverter -> PV Output Meter ->Utility AC Disconnect -> Utility Meter -

Utility Meter (Include existing meter serial number, meter form and class)

ELECTRICAL LOAD CALCULATIONS REQUIRED TO SUBMIT TO UTILITY

For a 6000 Inverter please use a 40A 2P Breaker. There is a shortage of 35A Breakers - 11.23.20

Electric Service Reqs

Taps are not recommended as they can fail with an outage but Permitting will need to confirm with the AHJ. If the AHJ allows, then Provo will side with the AHJ.

Placards

Meter / Transformer Pole:

Must be labeled to indicate potential electric current back feed. Provo City Power will provide and install labels when Customer's electric system is approved for Interconnection.

Over Current Device:

Shall be marked at the service panel to indicate power source and connection to the Provo City Power's Grid.

Label Page Notes

Reference Utah Labels block

Rate Schedule Link
link
Website
link
Phone
(801) 852-6852

Other details

Revision Required
Yes
Mod Swap Requires Planset
Yes
Compiled from public records, 2026. Tariffs and interconnection rules change; verify with Provo Power before you rely on this. The useful move: if an installer says you need a main panel upgrade, ask how these tap and interconnection policies were considered first.