Solar Sanity Checksolar, decoded Independent. Nothing you type leaves your browser.

SESD - South Utah Valley Electric Service District

Utah Utility Interconnection & net metering rules
Net Metering Allowed0
Supply Side Taps Allowed0
Line Taps Allowed0
Load Taps Allowed0

Net metering & export

Net Metering Allowed
0
Post Solar Billing Method
Export Rate
Solar Export Type
Fixed kWh
Solar Export Rate
0.051
Solar Export Value Notes
Rate changes from time to time.
Net Excess Generation Notes

NET FEED-IN TARIFF (NFiT): The customer consumes the electricity that is generated on the customer’s premises. Electricity supplied by the District is charged at the rates and fees listed below. Electricity generated by an eligible customer-operated renewable energy generator and fed back to the District’s electrical distribution grid is credited back to the customer’s kWh usage only at the NFiT rate listed below. 

Rebates Offered
0

Interconnection & taps

Approval Req To Install
Yes
Interconnection Level
3
Supply Side Taps Allowed
0
Line Taps Allowed
0
Load Taps Allowed
0
Automatic Transformer Upgrade Size
0
Meter Aggregation Allowed
0

System size & offset

System Size Restrictions
10
System Size Restriction Type
AC kW
System Size Battery Included
0
System Size Includes Existing Systems
0
Offset Type
No Restrictions
Offset Value
0
Offset Calculation Period
0
Industry Standard Watts Sqft
2
System Offset Notes

System Size: Limit at 10kW AC

Offset Calc Tool
N/A

Metering & disconnect

Meter Spot Process

Google WebForm for existing meter power upgrades, power line relocation or removal, disconnect/reconnects, etc

Allowed Meter Adapter
None

Plans & docs

SLD Reqs

Production Meter not required

For a 6000 Inverter please use a 40A 2P Breaker. There is a shortage of 35A Breakers - 11.23.20

Electric Service Reqs

Taps:

Supply and Line side taps are not allowed

Load Side taps are allowed

Label Page Notes

Reference Utah Labels block

Rate Schedule Link
link
Website
link
Phone
(801) 465-8020

Other details

Restrict Inspection
0
Revision Required
1
Mod Swap Requires Planset
1
Address ID
108114
Express Planset Eligible
Yes
Compiled from public records, 2026. Tariffs and interconnection rules change; verify with SESD - South Utah Valley Electric Service District before you rely on this. The useful move: if an installer says you need a main panel upgrade, ask how these tap and interconnection policies were considered first.