Community Electric Coop

Virginia Utility Interconnection & net metering rules

Spot something wrong?

Tariffs and interconnection rules move often. If something here is out of date or missing, tell us and we'll fix it.

Report a correction
Net Metering AllowedYes
NEM TypeAnnual
Line Taps AllowedNo
Load Taps AllowedNo

Net metering & export

Net Metering Allowed
Yes
NEM Type
Annual
TOU Utility
No
Post Solar Billing Method
Net Metering
Net Excess Generation Notes

For any billing period in which generation exceeds consumption, producing a billing period credit, the monthly charge shall be based only on the fixed charges of the customer’s standard tariff, and any charges that may be applicable per: (i) an excess facilities agreement and, (ii) a Commission-approved standby charge. Billing period credits will be carried forward and applied to offset future consumption charges as provided in Rule 20 VAC 5-315-50.

A net metering customer shall receive no compensation for excess generation unless the net metering customer has entered into a power purchase agreement with the Cooperative (Customer responsibility)

Rebates Offered
Yes

Interconnection & taps

Approval Req To Install
Yes
Line Taps Allowed
No
Load Taps Allowed
No
Automatic Transformer Upgrade Size
0
Meter Aggregation Allowed
Yes

System size & offset

System Size Restrictions
20
System Size Restriction Type
AC kW
System Size Battery Included
No
System Size Includes Existing Systems
No
Offset Type
Combination
Offset Value
100
Offset Calculation Basis
Historical
Offset Calculation Period
12
Industry Standard Watts Sqft
2
System Offset Notes
  • The utility has a very strict 100% usage restriction. The restriction is based off of the customer's previous 12 months of usage history.
  • AC may not exceed 20.00 kW
Offset Calc Tool
PV Watts

Metering & disconnect

Production Meter Required
No
Production Meter Position
N/A
Production Meter Labeling
N/A
Allowed Meter Adapter
None

Plans & docs

Site Plan Reqs
  • Requires a lockable, load-breaking manual disconnect.
  • The disconnect must be accessible to the utility 24/7. Cannot be obstructed.
SLD Reqs
  • Requires a lockable, load-breaking manual disconnect.
Website
link
Phone
(757) 242-6181
Compiled from public records, 2026. Tariffs and interconnection rules change; verify with Community Electric Coop before you rely on this. The useful move: if an installer says you need a main panel upgrade, ask how these tap and interconnection policies were considered first.