Lyndonville Electric Department
Net metering & export
- Net Metering Allowed
- 1
- NEM Type
- Monthly
- TOU Utility
- 0
- Post Solar Billing Method
- Net Metering
- Net Excess Generation Notes
Blended Residential Rate: $0.14025 per kWh
Excess generation will be calculated on a monthly basis by multiplying the excess kWh generation times the blended residential rate ($0.13943 per kWh). The cooperative will measure and calculate consumption versus production through separate meters, both owned by HED. Positive/Negative REC/Sitting Adjustors - PG 5&11
Production Meter cost: $121.33 "The cost of the meter is included in the customers monthly charges"
- Rebates Offered
- 0
- Deregulated
- 0
Interconnection & taps
- Approval Req To Install
- Yes
- Interconnection Level
- 3
- Line Taps Allowed
- 1
- Load Taps Allowed
- 1
- Automatic Transformer Upgrade Size
- 0
System size & offset
- System Size Restrictions
- 50
- System Size Restriction Type
- DC kW
- System Size Battery Included
- 0
- System Size Includes Existing Systems
- 0
- Offset Type
- No Restrictions
- Offset Value
- 0
- Offset Calculation Period
- 0
- Industry Standard Watts Sqft
- 2
- System Offset Notes
Up to 50kW
- Offset Calc Tool
- PV Watts
Metering & disconnect
- Production Meter Required
- Yes
- Production Meter Position
- Inv-PM-Disco-POI
- Production Meter Labeling
- Production Meter
- AC Disconnect Required
- Yes
- AC Disconnect Labeling
- Visible Lockable Labeled Disconnect
- Meter Spot Process
TDR Process "No true process"
TDR - Who to
TDR - Applications/Documents Req No applications required
TDR - ETA of notice required for request "Just call and we'll let you know" no timeframe given
TDR - Who can schedule? Does not matter
TDR - ETA of Utility Scheduling TDR "Just call and we'll let you know" no timeframe given
- Allowed Meter Adapter
- Tesla Backup Switch,ConnectDER
Plans & docs
- Site Plan Reqs
"A site plan is a construction drawing. All systems must provide a site plan or plans of the project containing the
following information:
a. The scale in feet and a representative fraction. The plan must be drawn to scale.
b. A compass orientation, legend, title and date.
c. An inset showing the location of the system within the Town.
d. Proposed facility location and any project features, including all described below. Indicate whether features
already existing or are proposed, (such as electric poles, access drives, etc.).
e. Property boundaries and setback distances from those boundaries to the corner of the nearest project related structure, Distances to any nearby residences, and dimensions of all proposed improvements.
f. The project limits of disturbance and the total acreage of any disturbed area, including any necessary and
associated distribution upgrades.
f. Proposed utilities, including the distance from source of power, sizes of service available and required, and
locations of any proposed utility or communication lines. Indicate whether utility lines are overhead or
underground.
g. A description of any areas where vegetation is to be cleared, altered, or mowed/managed during
construction or on an on-going basis during the operation of the facility.
h. A description of any proposed direct or indirect alterations to or impacts on wetlands or other natural
resources protected under 30 V.S.A. § 248(b)(5).
i. Detailed plans for any drainage of surface and/or sub-surface water and plans to control erosion and
sedimentation both during construction and as a permanent measure.
j. Locations and specific descriptions of proposed screening, landscaping, groundcover, fencing, exterior
lighting, and signs.
k. Plans of any proposed access driveway, roadway, or parking area at the project site, including grading,
drainage, and traveled width, as well as a cross-section of the access drive indicating the width, depth of
gravel, paving, or surface materials.
l. The latitude and longitude coordinates for the center of the proposed project.
m. The presence and total acreage of primary agricultural soils as defined in 10 V.S.A. § 6001 on each tract to
be physically disturbed in connection with the construction and operation of the net-metering system, the
amount of those soils to be disturbed, and any other proposed impacts to those soils.
n. The approved site plan from any Act 250 Land Use Permit applicable to the host parcel.
o. If not a preferred site, a description of the current site use. If in agricultural use, describe whether site is
pasture, hay crop, row crops, etc."
- SLD Reqs
Production meter required
"Provide copies of One-Line Diagrams showing the
generation facility equipment; this is required for all projects. Projects over
150 KW in size require the One-Line Diagrams to be signed and stamped by a
licensed Electrical Engineer (PE)."
- Meter Num Req SLD 3LD
- 0
- ESID Num Req SLD 3LD
- 0
- Rate Schedule Link
- link
- Website
- link
- Phone
- (802) 626-3366
Other details
- Restrict Inspection
- 0
- Address ID
- 206262
- Express Planset Eligible
- No