Cowlitz County Public Utility District

Washington Utility Interconnection & net metering rules
Net Metering Allowed1
NEM TypeAnnual
Line Taps Allowed1
Load Taps Allowed1
AC Disconnect RequiredYes

Net metering & export

Net Metering Allowed
1
NEM Type
Annual
TOU Utility
0
Post Solar Billing Method
Net Metering
Net Excess Generation Notes

If the electricity generated by the customer and distributed back to the District during the billing period exceeds the electricity supplied by the District, then the customer shall be billed for the appropriate customer service charge as other customers of the District in the same rate schedule and credited for the net excess kilowatt-hours generated during the billing period, with this kilowatt-hour credit appearing on customer’s bill for the following billing period. On March 31st each year, any remaining kWh credits will be awarded to the utility without any compensation to the customer.

Rebates Offered
0
Deregulated
1

Interconnection & taps

Approval Req To Install
Yes
Interconnection Level
3
Line Taps Allowed
1
Load Taps Allowed
1
Automatic Transformer Upgrade Size
0
Meter Aggregation Allowed
1

System size & offset

System Size Restrictions
25
System Size Restriction Type
AC kW
System Size Battery Included
0
System Size Includes Existing Systems
0
Offset Type
Combination
Offset Value
100
Offset Calculation Basis
Historical
Offset Calculation Period
12
Industry Standard Watts Sqft
2
Offset Calc Tool
Historical Usage

Metering & disconnect

Production Meter Required
Yes
Production Meter Position
Inv-Disco-PM-POI
Production Meter Labeling
Production Meter
AC Disconnect Required
Yes
AC Disconnect Labeling
Visible Lockable Labeled Disconnect
Allowed Meter Adapter
None

Plans & docs

Site Plan Reqs

Not Required for Interconnection Submittal

SLD Reqs

Standard

Electric Service Reqs
  • AC Disconnect is required and must be adjacent to the utility company meters.
  • Production Meter Socket Required
Placards
  • 2020 NEC labeling is required on the plans, and installed at the site per NEC requirements. Must be posted on the meter base, disconnects and transformers informing working personnel that a PV system is operating at the premise.
Electrical Stamp Required
0
Equipment Approvals
California Energy Commission
Meter Num Req SLD 3LD
0
ESID Num Req SLD 3LD
0
Label Page Notes

2020 NEC

Electrical Diagram Notes
  • Order of equipment on ELD = Inverter > Disco > PM > POI
Rate Schedule Link
link
Website
link
Phone
(360) 501-9546

Other details

Restrict Inspection
0
Revision Required
1
Mod Swap Requires Planset
0
Address ID
3842189
Express Planset Eligible
No
Compiled from public records, 2026. Tariffs and interconnection rules change; verify with Cowlitz County Public Utility District before you rely on this. The useful move: if an installer says you need a main panel upgrade, ask how these tap and interconnection policies were considered first.