Snohomish PUD
Net Metering Allowed1
NEM TypeAnnual
Line Taps Allowed1
Load Taps Allowed1
AC Disconnect RequiredSituational
Net metering & export
- Net Metering Allowed
- 1
- NEM Type
- Annual
- TOU Utility
- 0
- Post Solar Billing Method
- Net Metering
- Net Excess Generation Notes
The PUD shall purchase power from an eligible facility at a rate equal to the energy component of the retail rate at which the PUD provides electrical service to the facility. the customer shall receive a credit for all electric energy produced during a billing period in excess of the amount of electric energy supplied by the PUD during that period, such credit to be applied to the customer’s future electric bills. On March 31 of any calendar year shall be zeroed out with no further liability to the PUD and no credit to the customer for that balance.
- Rebates Offered
- 0
- Deregulated
- 1
Interconnection & taps
- Approval Req To Install
- Yes
- Interconnection Level
- 3
- Line Taps Allowed
- 1
- Load Taps Allowed
- 1
- Automatic Transformer Upgrade Size
- 0
System size & offset
- System Size Restrictions
- 0
- System Size Restriction Type
- No Restrictions
- System Size Battery Included
- 0
- System Size Includes Existing Systems
- 0
- Offset Type
- Percentage
- Offset Value
- 100
- Offset Calculation Basis
- Historical
- Offset Calculation Period
- 12
- Industry Standard Watts Sqft
- 2
- Offset Calc Tool
- Historical Usage
Metering & disconnect
- Production Meter Required
- No
- Production Meter Criteria
PUD does not require production meters. If the customer chooses to add one, it must be labeled on the one-line as "customer-owned"
- Production Meter Position
- N/A
- Production Meter Labeling
- N/A
- AC Disconnect Required
- Situational
- AC Disconnect Criteria
- Systems ≥ 25 kW: Require a visible, open, lockable disconnect switch that is always accessible to District personnel.
- Single-phase 120/240 V systems < 25 kW with a self-contained meter do not require a visible disconnect switch.
- AC Disconnect Labeling
- Visible Lockable Labeled Disconnect
- Allowed Meter Adapter
- None
Plans & docs
- Site Plan Reqs
Standard
- SLD Reqs
- Electric Service Reqs
- Meters and Service Entrance Equipment Requirements: Section 5 Meters and Service Entrance Equipment (snopud.com)
- Install Reqs
- Customer is required to supply, install and maintain meter mounting equipment
- Metering shall not be mounted on district poles, padmount transformers or transclosures.
- No customer owned equipment may be installed between the meter mounting equipment and a district meter
- Placards
- Meters must be permanently labeled “Net Meter” in compliance with ESR.
- Use engraved phenolic labels with plain block letters or numbers on a contrasting background.
- Letters must be at least ½" (12.7 mm) tall unless larger size is required.
- Labels must clearly indicate the unit served by each meter.
- Place labels so they are readily visible and do not cover existing printed or labeled information.
- Attach labels smoothly with no overlaps, protrusions, or sharp edges.
- Do not place labels over existing phenolic labels.
- Labels may have self-adhesive backs, but must also be secured with at least 2 pop-rivets or screws (larger labels: at least 4).
- All labels must be installed and secured before acceptance.
- Exercise caution when drilling or installing fasteners to avoid contact with conductors.
- Electrical Stamp Required
- 0
- Equipment Approvals
- California Energy Commission
- Meter Num Req SLD 3LD
- 0
- ESID Num Req SLD 3LD
- 0
- Website
- link
- Phone
- (425) 783-1700
Other details
- Restrict Inspection
- 0
- Revision Required
- 1
- Mod Swap Requires Planset
- 1
- Address ID
- 4278928
- Express Planset Eligible
- Yes