MGE - Madison Gas and Electric Company

Wisconsin Utility Interconnection & net metering rules

Spot something wrong?

Tariffs and interconnection rules move often. If something here is out of date or missing, tell us and we'll fix it.

Report a correction
Net Metering AllowedYes
NEM TypeMonthly
Supply Side Taps AllowedYes
Line Taps AllowedYes
Load Taps AllowedYes
AC Disconnect RequiredYes

Net metering & export

Net Metering Allowed
Yes
NEM Type
Monthly
TOU Utility
No
Post Solar Billing Method
Net Metering
Net Excess Generation Notes
  • PG-1 - Parallel Generation - For interconnected PV systems of any size
  • PG-2 - Parallel Generation: Net Metering - For interconnected PV systems up to 100 kW (default rate) - Net metering is a rate option that credits the customer’s MGE bill at the appropriate retail rate for any electricity generated from the PV system that flows back onto the electric distribution system. If over the previous 12-month period the amount of electricity from a PV system sent to the electric distribution system exceeded the amount of electricity used, the customer is a net seller to the electric distribution system. Net sellers are credited at a different rate for a portion of electricity generated.
  • For more information, the customer can.
Rebates Offered
Yes
Deregulated
No
Allows Standby
Yes

Interconnection & taps

Approval Req To Install
Yes
Supply Side Taps Allowed
Yes
Line Taps Allowed
Yes
Load Taps Allowed
Yes
Tap Criteria

Taps allowed, but only in MSP

Automatic Transformer Upgrade Size
0

System size & offset

System Size Restrictions
0
System Size Restriction Type
No Restrictions
System Size Battery Included
No
System Size Includes Existing Systems
No
Offset Type
No Restrictions
Offset Value
0
Offset Calculation Period
0
Industry Standard Watts Sqft
2
System Size Justification
Load Justification

Metering & disconnect

Production Meter Required
No
Production Meter Position
N/A
Production Meter Labeling
N/A
AC Disconnect Required
Yes
AC Disconnect Labeling
Visible Lockable Labeled Disconnect
Allowed Meter Adapter
None

Plans & docs

Site Plan Reqs

• Location of exterior interconnection disconnect switch

• Adjoining street name

• Street address for the exact location of the distributed generation facility

• Location of major equipment

• Electric service entrance

• MGE electric meter

• Interface equipment

• MGE Transformer or utility pole

The Utility meter and utility disconnect switch must be within 10' of each other

SLD Reqs

All Jobs

  • Lockable interconnection disconnect switch with a visual open (call out "visual open" next to the disconnect on the drawing)- must be located outside as close to the transformer or service entrance as possible
  • Show voltage rating of AC Disconnect
  • Method of grounding (generator and transformer ground connections)
  • Size of installation (kW-AC)

Battery Jobs:

  • For whole home backup situations, a Fused Disconnect must be installed between the Utility Meter and Backup Gateway. No Other Disconnects are required for these configurations.

Multiple Disconnects

  • Must be labeled appropriately - "1 of 2", "2 of 2", etc.
Install Reqs
  • MG&E requires us to schedule a disco/reco with them for any type of electrical work (meter or MSP). If we’re touching their equipment they must be onsite, regardless of the licensed electrician.
  • The customer is required to furnish and install an external interconnection disconnect switch that opens with a visual break, is accessible at all times, is located for ease of access to MGE personnel, and shall be capable of being locked in the open position to facilitate safe and reliable operation of MGE’s electric distribution system.
  • The utility meter must have a 3' frontal clearance and unobstructed working space. It must be located at least 3' from the gas meter if applicable.
  • The AC disconnect must have 3' frontal clearance and unobstructed working space.
Placards
  • Placards as required per NEC 690. Placards are engraved plastic, brass, or aluminum and at least 1/2" tall
  • AC disconnect: label with the following wording: “RAPID SHUTDOWN SWITCH FOR SOLAR PV SYSTEM” & “MGE UTILITY DISCONNECT SWITCH" and should be no more than 3’ from the switch.
  • Utility meter: Label indicating PV system connected, on utility meter "DUAL POWER SOURCE SECOND SOURCE IS PV"
Website
link
Phone
(800) 245-1125

Other details

Revision Required
Yes
Mod Swap Requires Planset
Yes
Compiled from public records, 2026. Tariffs and interconnection rules change; verify with MGE - Madison Gas and Electric Company before you rely on this. The useful move: if an installer says you need a main panel upgrade, ask how these tap and interconnection policies were considered first.